Tuesday, July 10, 2012

Catch the Progress on the Pipe Rack Line 5 Progress

It's been almost a month since Water Treatment Plant Project Line 5 is start, and it's really takes a lot of times and energy for me. While the other project which is Pipe Rack Line 5 is almost reach the Dead Lines and that means all the water lines has to hand over to the users in July, 25, 2012, and that's mean we only have few weeks to finish all the water lines in the pipe rack line 5.

Piping and Fabrication now will talk about what is the problems on this pipe rack line 5 project, and how can we solve all the problems? After we had a meeting with all the leaders, including staff from the center office, we decide that all the critical lines must be start with special teams and all the requirements for them we have to provide everything what they wants, including consumables, equipment and even transportation to mobilize the material to the site.

So, I have to send two welders on WTP Project to Pipe Rack, because they are also need more welders to complete the task "On Times". Even now I have to think harder, how do I have to catch the progress with less welders? I hope there is another solutions for me and my teams, also for Pipe Rack teams.