After almost a few months Piping & Fabrication not posting, because of the Water Treatment Project (WTP) is still on the progress, so I can't do much on the office, cause I have to supervise and control the project and make sure that project is running well.
After almost more than a month, our WTP project is already reach 46% from total 12000 inch dia, and it still doesn't make me happy because we don't have enough worker to do that project (less workers). But, on the other side Piping and Fabrication feel so happy that we can prove to everyone, even we only have no more than 20 persons, but we still can reach more than 45% until now.
So much people doesn't believe that me and my team can do the WTP project in time, but we already prove it to anyone that we can do it and silent them with that progress.
and for everyone, Minal Aidin Wal Faidzin (Mohon Maaf Lahir dan Bathin). Thank you very much.
No comments:
Post a Comment