Friday, June 15, 2012

ERECTION PIPE AT WATER TREATMENT PLANT

This is really exhaust day to all of us at site project, including myself. with Piping and Fabrication, I will share the experience when me and my team has to finish Shutdown with only four hours limitation, because the machine will running again. 

With all the preparation that we already prepare about few days ago, everything almost run according to the schedule, except in few line that I have to cut and re-weld pipe line DN300 because it's not has good gap to weld. And when we have to finish all the line with 4 hours left, so we do anything necessary to finish the job so the plant can running again.

I know this experience with Erection Pipe at Water Treatment Plant during Shutdown will never forget, because we have small bonus from the users and that's make me and my team work as harder we can do. and here it is few pictures when we do the erection pipe DN300 and install valve at Water Treatment Plant.

Erection Pipe

Cut and Re-Weld Pipe

The Pipe has been joined

That's all what Piping and Fabrication can told about Erection Pipe at Water Treatment Plant during 4 Hours Shutdown.

Tuesday, June 5, 2012

Urgently Job for Hot Tapping at WTP Project

I know this is too hard for me to do it myself, not even if I have to do with my teams but if there is no equipment and mobilization for our teams, it's impossible to finish this WTP Project on time. Not mention for Hot Tapping Job, it's really urgent, because we can't stop the machine or request for shut down, that's will stop all the production process.

And with all the Piping and Fabrication job about 12 thousand Inch Dia, I think I have think another strategy for this WTP Project. Including all the report and material issue that has been delayed for few days. But, I believe this will get better soon, same as like Pipe Rack Project. I hope.