Wednesday, October 31, 2012

Finished Hydro Test for Sand Filter or Multigrade Line

Finally we can completed the Sand Filter Line with finished Hydro Test 10.7 Bar. Piping and Fabrication just want to inform all of you that Sand Filter Line is Done, just few more Joint to the Suction Pump and we plan that will finish fabrication and install in this week.

 10.7 Bar Pressure on Hydro Test Display on Pressure Gauge at 14.45 WIB

Pressure still remain 10.7 Bar on the one hour Holding Time

And now we can focus to the Additional Work for WTP Project such as Fill Softener Tank with Resin, Modification Frontal Piping on Softener Tank, etc.

We never boring to Thanks to the teams and anyone who get involves in this WTP Project. Congratulations Teams, We still have Raw Water Drawing 1 waiting to get our touch. 

Sunday, October 21, 2012

Evaluation for Water Treatment Project

In the end of Water Treatment Project for all the lines such as Filter Water, Soft Water, Raw Water, Sand Filter, Dynasand and etc, including all the Equipment or Tank, Multigrade Tank, Softener Tank and Demin Water Tank, there is so many thing we can learn from that project.

It's really hard to control people or can we call Man Power, because we have a big hope to them, when we hire them, they will do as professional worker, but the fact is we have to make them work, teach them how to work, and told them how to work and that's really such a big problem for me and my team. But, we have to take that responsibility, because we can't hire another worker, they all the same, mostly they can't work especially helper.

Luckily that we had very competent and good leader, so they can arrange all that worker, even we know that's really hard but we have to use them. Not mention the users want to do this, want to do that, like they never know the problem on the field, everything can goes wrong if we push them too much.

Piping and Fabrication only hope everyone will understand that we already work as maximum as we can, as hard as we can and we can do nothing more than it, this is the best what we can do for now. We hope, we really hope.

Thanks for everyone who supporting us to finish this WTP Project, especially my teams, once again thank you very much.

Wednesday, October 17, 2012

Soft Water Line is Done

Same like Filter Water, Raw Water and Dynasand, Soft Water is Done and we already finish Hydro Test for Soft Water too. Piping and Fabrication will inform this to all of you just to inform to anyone who involve with this process.

But, still there is still plenty of work that we must done in short of time, next is Sand Filter and Softener Tank. Under my supervise and Mr. Fandi, we will try to finish Softener Tank this week, because next week all line has to running to supply water for Fiber Plant Line 5.

Once again, thank you to everyone who involve with this project and of course my team, congratulation Teams! I don't know how to thanks to all of you, because I've seen myself that Soft Water Line drawing is really different with actual site condition, there is too many modification we have to do, such as cut and re-weld, different size, different elevation, etc.

Saturday, October 6, 2012

Filter Water Line is Completed with Successful Hydrotest

I know it's been a little bit late when I inform this, because probably it's almost few weeks ago that Filter Water Line is completed. We are glad that we can finish the Filter Water on time, of course with much help from my teams and the others. Without them, we are nothing. Filter Water Line completed with Hydro Test process with almost 11 Bar Pressure and we found no leakage.

Here it is the pictures of Hydro Test, we start from 16.45 to fill the water in, and at 17.50 the pressure start stabilize and we start holding time about 1 hour and finish about 19.00 WIB. This is Piping and Fabrication Reporting.

Pressure at 11 Bar for Filter Water Hydro Test

Starting Holding Time at 17.50

Filter Water is Completed

Once more we are thanks to someone always helping us which is Mr. Pandi, because he always lead us and warn us if there is some problem with our job, and of course to my teams, Congratulations Teams!

Wednesday, October 3, 2012

Replace DN1400 Outlet Dynasand with The New One

May be this DN1400 Outlet Dynasand it's too old, too many corrosive and need to be replace with the new one, and on the Water Treatment Plant (WTP) Project, Replacing DN1400 Outlet Dynasand is one of the line that we have to finished as soon as possible.

Piping and Fabrication has few pictures when we replacing the Old DN1400 Outled Dynasand with the new one, smaller but more effective. And also thank you to everyone who involves with this job and once again thank you very much.

DN1400 Outled Dynasand (previous)

Erection DN800 Pipe Outled Dynasand (Processing)


DN800 to DN600 Outlet Dynasand (New One)

I hope all the line can finish on time without any major problem. Thanks for visiting and good luck!