Wednesday, October 3, 2012

Replace DN1400 Outlet Dynasand with The New One

May be this DN1400 Outlet Dynasand it's too old, too many corrosive and need to be replace with the new one, and on the Water Treatment Plant (WTP) Project, Replacing DN1400 Outlet Dynasand is one of the line that we have to finished as soon as possible.

Piping and Fabrication has few pictures when we replacing the Old DN1400 Outled Dynasand with the new one, smaller but more effective. And also thank you to everyone who involves with this job and once again thank you very much.

DN1400 Outled Dynasand (previous)

Erection DN800 Pipe Outled Dynasand (Processing)


DN800 to DN600 Outlet Dynasand (New One)

I hope all the line can finish on time without any major problem. Thanks for visiting and good luck!

Friday, September 28, 2012

All The Line on WTP Project has to Finish on 15 October 2012

Bad News for our team, WTP Team, we have to finish all the Line, including sand filter and soft water line at October, 15, 2012, and that's really make me and my teams have to think and work faster. Piping and Fabrication try to find the solution for this situation, and we really hope that we can finish this project on time.

Not mention I have another instruction that the Raw Water Line need to revision again, because we have to follow the process department with they new ultrasonic flow meter. And also they want to finish the revision only on three days and I just can hope there will be no Re Hydro Test for that line.

Tuesday, September 18, 2012

Completed Line Raw Water Drawing 1 & 2

Finally we completed Raw Water Line for Drawing 1 & 2 (Inlet Actiflo), and we also already completed Radiography, Flushing and Hydro Test for the line. Me and My Team finished this Raw Water or Actiflo Line in time, even we know there is still a few problem during that process but, finally we made it. Thank you to anyone who get involve with this job and this is few pictures and photos when Piping and Fabrication doing Flushing and Hydro Test.

 Flushing Process

 Flushing Process

 Hydro Test at 10.7 Bar Pressure


And the good news is, there is no leakage found during that process and Congratulation Teams!

Thursday, September 13, 2012

How Can I Finish This WTP Project?

That's the question that I want to ask to my Boss, because I can't get enough tools, enough man power and enough times to finish this WTP Project on times. Not mention all the tank and equipment that we have to setting up in the same times. That's why me and Piping & Fabrication will talk to the boss and make decision to add more tools, man power (quality man power) and also all the facility I need.

I think that's the only way to get this project finish on time or the company will loose much money and times if the project delay or can't finish in time.

Friday, September 7, 2012

ERECTION MULTIGRADE (SAND FILTER) TANK

Finally Multigrade Tank arrived in the SPV Plant and me and my team can start erection the tank. Because if this multigrade tank not finish erection yet, the others job will be delay by it. And Piping and Fabrication show the pictures of the process of Multigrade Tank when it erection, put the tank on the base.



Monday, August 20, 2012

Piping Erection for Filter Water Line


Continuing again with WTP Project, and now at Demin Plant, we doing Piping Erection for Filter Water Line. It’s really hard place to do the piping erection, because we do this erection inside Demin Plant building and we only have small space and we can’t make any mistake. Because if something goes wrong, the existing pipe and tank will crush by that pipe.

 Manually Piping Erection at Demin Plant

With a very little space between the wall and existing pipe and tank, 
we have to do piping erection manually

So we really have to extra carefully in this process, and Piping and Fabrication believe that our man can do this one, because they have experience for this kind of situation. 

The planning is, after we complete all this Filter Water Line, and all the support and civil work is complete also, we will make this team to do the erection in the same location with another line, which is Soft Water Line, but we still waiting for that time, and I hope that will happen soon.

Wednesday, August 15, 2012

Water Treatment Project Still on The Way

After almost a few months Piping & Fabrication not posting, because of the Water Treatment Project (WTP) is still on the progress, so I can't do much on the office, cause I have to supervise and control the project and make sure that project is running well.

After almost more than a month, our WTP project is already reach 46% from total 12000 inch dia, and it still doesn't make me happy because we don't have enough worker to do that project (less workers). But, on the other side Piping and Fabrication feel so happy that we can prove to everyone, even we only have no more than 20 persons, but we still can reach more than 45% until now.

So much people doesn't believe that me and my team can do the WTP project in time, but we already prove it to anyone that we can do it and silent them with that progress.

and for everyone, Minal Aidin Wal Faidzin (Mohon Maaf Lahir dan Bathin). Thank you very much.