Tuesday, September 18, 2012

Completed Line Raw Water Drawing 1 & 2

Finally we completed Raw Water Line for Drawing 1 & 2 (Inlet Actiflo), and we also already completed Radiography, Flushing and Hydro Test for the line. Me and My Team finished this Raw Water or Actiflo Line in time, even we know there is still a few problem during that process but, finally we made it. Thank you to anyone who get involve with this job and this is few pictures and photos when Piping and Fabrication doing Flushing and Hydro Test.

 Flushing Process

 Flushing Process

 Hydro Test at 10.7 Bar Pressure


And the good news is, there is no leakage found during that process and Congratulation Teams!