For almost few weeks, Piping and Fabrication can't post this blog, because there is too many problems that I have to solve for Pipe Rack Line 5 Project, and one of them is Sandblast and Painting. We already told to our Sub contractor that all the Steam Line Pipe has to paint with Heat Resistance Paint, including all the support such as shoe and etc. But, when we inspect to the field, they don't do paint as we told. They do the painting without Heat Resistance Paint and that's make our progress delay, because they have to do reworks.
Not mention all the weather problem such as rain, because we can not avoid it, when the rain falls, almost every activity on the Pipe Rack is stop to avoid accident. Now our progress is almost 15% left behind and that's make me have to think, how do I have to cover all those 15%?
This is Piping and Fabrication, I hope this project will finish soon and all the problems will disappear. Thanks for visiting and if you have a suggestion, please comment!